Monday 4 January 2010

Dewsbury Town Hall External Refurbishments Commences Jan 2010

Over the coming year we will be carrying out a major £3m building project on the exterior of dewsbury town hall.

Work includes:-
- Repairs to the roof and stonework
- A new roof for the concert hall
- Replacement or repairs to windows
- Secondary glazing
- Improved flag flying provision
- Roof Insulation

The works will be phased to reduce disruption to hirers and main stage events. During the phasing certain rooms will have to be closed due to the exterior building works. There will be four phases of work continuing until April 2011:-

Phase One - Old Wakefield Road (January to June 2010)
Phase Two - Front of the building (June to August 2010)
Phase Three - Above the Concert Hall (July - November 2010)
Phase Four - Town Hall Way (November 2010 - April 2011)

To keep track of what is happening with the improvements please follow Kirklees Town Halls on Twitter and Facebook or keep an eye this blog!

No comments: